Safety

Galvanised steel structures with great durability, interconnected in order to make them more stable and safe in the event of an earthquake.

Quality

The materials are manufactured in certified industrial facilities according to high-level quality control systems.

Speed of Construction

The Wig Light Steel Framing systems are smart and light for easy and speedy installation. Deadlines fall by more than 50%.

Freedom

This system enables construction according to the project. There are no architectural limitations, or even appearance, whether the design is traditional or modern.

Comfort

The thermal and acoustic comfort levels of our houses are much higher than those built in a traditional way due to the insulating materials used and the lack of thermal bridges in the wall

Ecology

Energy savings and the fully recyclable materials make the Concept Casa buildings environmentally-friendly.

Efficiency

Energy efficiency due to the high level insulation.

Guarantee

Manufacture and installation by reference companies, Ciccopn-certified buildings and partnerships for technological development with IPL.

We are skilled to build your quality dream house

PHASE 1

Project design or use of a prepared project

  • Preliminary architecture study
  • Final architecture project
  • Remaining projects for licensing

PHASE 2

Manufacture of Wig Light Steel Framing structures

  • Production of Wig Light Steel Framing profiles
  • Remaining projects for licensing

PHASE 3

Foundations

  • Land preparation
  • Concrete foundations according to project

PHASE 4

Mounting the Wig Light Steel Framing structures

  • Mounting the Wig Light Steel Framing profile panels
  • Insulation between the structure and concrete elements
  • Anchoring the structure to the concrete base

PHASE 5

Exterior Walls

  • Exterior cladding with OSB sheets
  • Waterproofing sheets with steam membranes

PHASE 6

Sandwich panel roof covering

  • Installation of a structure for the pendant
  • Installation of OSB sheets
  • Waterproofing with a steam membrane
  • Installation of gutters
  • Installation of sandwich panel and fixtures

PHASE 7

Flat roof covering

  • Installation of OSB sheets
  • Waterproofing with a steam membrane
  • Installation of gutters
  • Installation of waterproofing lining

PHASE 8

Exterior wall sheathing

  • Installation of insulation on the outside
  • Application of mortars
  • Application of priming treatment
  • Application of final product
  • Application of any other finishing according to the client’s choice, such as stone, wood, viroc, phenolic film, etc.

PHASE 9

Frames

  • Application of window sills
  • Application of window frames

PHASE 10

Interior walls

  • Application of stone wool insulation
  • Application of plaster boards
  • Final finishing

PHASE 11

False ceilings

  • Application of stone wool insulation
  • Application of plaster boards
  • Final finishing

PHASE 12

Equipment, kitchen, toilets

  • Application of pavements and interior linings
  • Installation of toilet equipment
  • Installation of kitchen
  • Installation of closets
  • Other finishings
Browse some of our works Browse Works